School starts for years 8/9/10 tomorrow. Today in system development:
  • Uploaded past papers: year 11 3U half yearly, prelim
  • Discovered that free/open source software tool Ant Renamer works quite well for mass-renaming files
  • Made change to schedule:
    • Due to the large amount of material collected before the start of the 2009 school year, the size of which was unforeseen during the production of the original schedule, not all existing intranet material has been uploaded to the new intranet
    • It is the mostly senior past papers that have not yet been uploaded
    • As a result, item 12 of the Gantt chart has been prolonged indefinitely
    • I aim to finish uploading the past papers for the seniors before public prototype release.